Fastener spacing and application is the same except that fasteners are to be installed in the corrugation valleys as opposed to the crests.
Suntuf roof panels installation.
Step 3 purlin spacing.
Sheets will arrive with labels showing this side up and it is very important to install the sheets in the correct orientation.
This will ensure adequate water runoff.
Where possible ensure that your roof pitch is at least 10.
Allow for the sheet to overhang the lower purlin by 50 mm.
Closure strips are not required for vertical installations.
Suntuf is supported.
Vertical installation of suntuf is essentially the same as with roofing canopy applications.
Step 2 pitch.
Measure the width of your structure and divide by 760mm this will give you the amount of suntuf sheets.
How to install step 1 measure.